COUNTY HWY V – coming into Grafton also under construction starting July 8th

Weather can change this schedule.  

starting on Monday, July 8th,  milling about 2.5” off of the highway this should take about 2 days.

The following week, Monday, July 15th,  re-pave 2.5” back into place.   That should take about 2 weeks.

While work is being done the highway will be closed unless someone’s trying to get to their house within the work zone. 

Any questions, comments, or concerns, please contact Jon Edgren  Public Works Director Oz Co Highway Dept  262-238-8335